Radial Magnets, Inc.we know magnets

Radial Magnets · Technical Resource

Second-Source Qualification Playbook

Dual sourcing is the standard answer to supply risk, and on magnets it is usually done wrong — two vendors buying from the same furnace, or a second source approved on paper that has never shipped a production lot. A magnet second source is a metallurgical qualification, not a commercial one, and it has to be built before you need it. This is the protocol.

for: supplier quality · procurement · design engineering · program management

last reviewed — july 2026

Contents

  1. What actually counts as a second source
  2. Deciding which parts justify it
  3. The qualification protocol
  4. The cross-comparison matrix
  5. What triggers requalification
  6. Running two sources in production
01

What actually counts as a second source

The test is simple and most dual-source arrangements fail it: if the disruption you are insuring against occurred, would the second source still be able to ship?

Degrees of independence. Each row removes a shared point of failure — and adds qualification cost.
ArrangementIndependent ofStill exposed toReal resilience
Two distributors, same millCommercial failure of one distributorMill capacity, country risk, export licensing, alloy supplyAlmost none
Two mills, same countrySingle-facility events — fire, capacity, quality holdCountry-level export controls, tariffs, regional disruptionModerate
Two mills, different countriesCountry-level regulatory and tariff eventsUpstream alloy and rare earth concentrationGood
Two mills, different countries, different alloy supplyMost single-point failuresSystemic rare earth market eventsStrong — and expensive
Domestic stock plus an overseas millBorder and transit events on the buffer quantityEverything beyond the buffer durationGood for the covered window

Verify the mill, not the vendor

Two distributors quoting the same part at similar prices are frequently sourcing from the same facility — the magnet manufacturing base is more concentrated than the vendor base. The check takes one email: ask each supplier which facility presses and sinters the part, by name and address, and compare the mill named on the material certificates you already hold. If they match, you have duplicated your purchasing overhead and insured against nothing.

The three things that make magnets harder than most components

tooling is source-specificThe press die and magnetizing fixture live at one mill. A second source needs its own set — a real cost, a real lead time, and the reason second-sourcing must start long before it is needed.
process defines the productTwo mills working to the same grade specification produce measurably different parts. Alignment field, sinter profile, grain structure and plating chemistry all differ, and all show up in the numbers. Grade equivalence is not part equivalence.
the failure mode is invisibleA second-source part that is 4% weaker fits, assembles and passes visual inspection. It surfaces as a calibration shift or a field failure months later — which is exactly why cross-qualification has to be quantitative.
02

Deciding which parts justify it

Second-sourcing every magnet part number is neither affordable nor necessary. Score the portfolio and spend the qualification budget where interruption actually hurts.

FactorRaises priority whenLowers priority when
Consequence of stockoutStops a production line or a shippable productBuffered by inventory or substitutable
GradeSH, UH, EH, AH or SmCo — export-licence exposedStandard N-series, widely produced
GeometryCustom tooled, unusual, or tight toleranceClose to a catalogue size available from many sources
Qualification burdenLow — industrial part, simple acceptanceHigh — full PPAP with customer approval required
VolumeHigh enough to interest a second millBelow a viable MOQ at a second source
Program lifeYears of remaining productionApproaching end of life — a last-time buy is cheaper

The cheaper alternative, where it fits

For many parts, an inventory buffer is a better purchase than a second source. Qualifying a second mill costs tooling, samples, engineering time and often a customer approval cycle, and it delivers nothing until it is used. Holding an extra ten weeks of cover costs carrying charges and delivers immediately. Second-sourcing wins where the risk is long-duration — export controls, capacity loss, a supplier exiting — because no realistic buffer covers those. Buffering wins where the risk is a delivery slip. Most portfolios need both, on different parts. See inventory programs for buffer sizing.

03

The qualification protocol

Six stages. The discipline that matters is that each gate is passed before the next begins — the common failure is jumping from samples straight to production because a shortage arrived first.

QUALIFICATION GATES 1 · PAPER audit, capability, certificates 2 · TOOLING die + magnetizing fixture 3 · SAMPLES first article vs. incumbent 4 · FUNCTION in-assembly test, thermal, life 5 · CAPABILITY production run, Cpk, PPAP 6 · RELEASE split allocation, keep it warm Typical elapsed time — 16 to 30 weeks for an industrial part; 6 to 12 months where customer approval of a PPAP submission is required. Stages 2 and 5 dominate the schedule. Neither compresses under commercial pressure, which is why a qualification started during a shortage arrives after the shortage has resolved itself.
Start the qualification when supply is comfortable. It cannot be completed during the event it protects against.

Stage 1 — Paper qualification

Stage 2 — Tooling

Stage 3 — First article and cross-comparison

The core technical gate. Measure incumbent and candidate parts on the same equipment, on the same day, at the same temperature. Comparing the candidate against the incumbent’s certificate rather than against incumbent hardware measured yourself is the most common methodological error here.

Stage 4 — Functional validation

Stage 5 — Capability

Stage 6 — Release and maintenance

04

The cross-comparison matrix

What to measure on both sources, and what an acceptable difference looks like. Some variation between mills is normal and expected; the point of the exercise is to establish that it sits inside your design margin rather than inside your ignorance.

Measure incumbent and candidate together, same equipment, same session, same temperature. Sample at least 30 pieces per source where the quantity allows.
CharacteristicMethodTypical acceptable differenceWhy it matters
Total magnetic momentHelmholtz coil and fluxmeterMeans within a few percent; candidate spread no wider than incumbentThe primary acceptance characteristic — a systematic offset shifts every downstream calibration
Br, Hcb, Hcj, BHmaxPer-lot material certificateBoth above grade minimums; note where each sits within the bandA source running near the minimum has less margin against thermal excursions
Demagnetization behaviourB-H curve at maximum service temperatureKnee position outside the operating region for bothTwo parts meeting the same room-temperature grade can behave differently hot
Critical dimensionsMetrology per ballooned drawingBoth within tolerance; compare where each centres in the bandTwo sources centred at opposite ends of a tolerance make a mixed-lot assembly problem
Coating thickness per layerXRFBoth within specificationAffects press fits, bond strength and corrosion life
Coating adhesionCross-hatch, thermal shockBoth passAdhesive bonding behaviour differs between platers
Corrosion resistanceSalt spray per ASTM B117Both meet the specified hoursThe most common real difference between mills
Pattern accuracyRotary Hall pole scanPole placement and balance within the same limitsEncoder and sensor accuracy depends on it entirely
Mechanical integrityChip and crack rate over the sampleComparable; grinding practice differs materially between millsDrives assembly line scrap
Thermal exposure responseFlux measured before and after worst-case cyclingIrreversible loss comparable and within design marginThe test that catches a source running thin on coercivity

Do not set acceptance limits from the incumbent alone

Limits derived only from the incumbent’s output encode that supplier’s process centring as though it were a requirement. A candidate that is entirely conforming then fails, and a legitimate second source is rejected for being different rather than for being unacceptable.

Set limits from what the design needs, established by analysis and validated against both sources. If that exercise reveals the design has been relying on the incumbent running consistently above the minimum, that is an important finding about your design margin — and it is better to learn it during a qualification than during a shortage.

05

What triggers requalification

Qualification is a state that decays. These are the events that should reopen it, and the change-control clause in your supply agreement is what makes sure you hear about them.

ChangeRequalification scopeRationale
Different manufacturing siteFullEffectively a new source, whoever owns it
Alloy supplier changeMaterial properties and thermal validationComposition and grain structure shift
Grade or composition changeFull magnetic and thermalIncludes reduced-Dy reformulations — see alternatives
Plating line or chemistry changeCoating thickness, adhesion, corrosion, and any bonded-joint validationAdhesive behaviour and corrosion life both change
New or repaired toolingDimensional and magnetic first articleDimensional shift and pattern change
Magnetizing fixture changeMagnetic and pattern verificationSaturation level and pole placement
Extended production gapAbbreviated — first article on resumptionProcess drift and personnel turnover
Significant nonconformanceScoped to the failure modeConfirms corrective action actually worked

The clause that makes this work

None of the above helps if changes arrive silently. The supply agreement should require written notification before any change to manufacturing site, alloy source, grade composition, coating process, tooling or magnetizing method, with an agreed notice period and your right to requalify before the changed parts ship. Without it, the first indication of a mill change is a batch that measures differently, discovered by whatever sampling plan happens to be running. The full term sheet is in commercial terms.

06

Running two sources in production

A qualified second source that never ships decays into a name on a list. Keeping it viable requires deliberate allocation and a little discipline about lot control.

Allocation

SplitEffectSuits
100 / 0 with a dormant approvalCheapest; qualification decays and the second source has no tooling warmLow-risk parts where the approval is a formality
90 / 10Keeps tooling exercised and the relationship live at minimal costThe practical default for most critical parts
70 / 30Second source can scale quickly; meaningful pricing tensionHigh-volume, high-consequence parts
50 / 50Maximum resilience; loses volume pricing at both and doubles quality oversightRarely justified outside safety-critical supply

Ten percent is usually the right number

A minority allocation large enough to require a real production run once or twice a year keeps the tooling exercised, the operators familiar, the account commercially interesting and the qualification current — at a small premium over single-source pricing. It also gives you continuous evidence that the second source still performs, rather than an assumption you will test for the first time during an emergency.

Lot control across sources

The scenario worth rehearsing

Your primary source is interrupted. Before you switch, confirm four things: the second source’s tooling is present and serviceable, its qualification has not been invalidated by an unnotified change, its current lead time from a standing start, and whether your customer requires notification of a source change. Every one of these is faster to establish now, on a quiet afternoon, than during the interruption — and a second source that fails any of them is not the insurance you believed you had bought.

Be the second source, or find you already were the first

We qualify as an alternate source on existing magnet part numbers regularly — working from your drawing, your acceptance limits and your first-article data rather than asking you to redesign around us. Send the print and the current supplier’s certificate and we will tell you honestly whether we can match it.

Related resources